Shutter is designed to be used as a part of slurry bailer during cement bridge installation to isolate productive horizons and wellbore sections during operation and repair. In standard version they are manufactured in diameter of 108 mm (for TBG-89), 89 mm (for TBG-73), 78 mm (for TBG-60). Fabrication to required diameter as per customer’s specification or fabrication of an adapter to the required size is possible.
Shutter is designed to work with tubing joint as slurry bailers as well as with casing strings of different diameters slurry bailers. It is additionally completed with an adapter according to a customer’s specification.
It is a component of non-explosive technology proposed by “PGFS” LLC for installation of isolation bridges in a well by non-explosive method.
Shutter is designed to be used as a part of slurry bailer during cement bridge installation to isolate productive horizons and wellbore sections during operation and repair.
During preparatory operations, when filling bailer with cement , the rod is temporarily secured with lock pin, and bailer is screwed into a sleeve connected by thread to the housing with a glass membrane and rubber washers pre-installed in the housing.
Lock pin is removed before running the bailer into the well.
The release of bailer from the cement slurry occurs as a result of destruction of the glass membrane after the rod strikes the bottomhole and moves.
It is recommended to run into the well at speed of no more than 5000 m/h.
At 50 m before downhole the speed should be reduced to 350 m/h.
Time before rerunning the bailer with a shutter depends on setting rate of cement slurry (on its composition, pressure and temperature in the interval of bridge setting) and is an average of 3 hours.
In some cases, in case of high density and height of cement slurry column
Implementation options:
In case of 108 mm casing diameter for TBG -89, in case of 102 mm casing diameter for TBG -73 or for tubing 89 mm, in case of 78 mm casing diameter for TBG-60 or for tubing 78 mm, other dimensions upon Customer’s request.
Is a component of non-explosive technology proposed by “PGFS” LLC to install isolating bridges in a well by non-explosive method.